防水材料施工工艺
Construction Technology of Waterproof Material
1、将液体添加剂倒入干净的搅拌容器中,然后按比例一边搅拌一边缓慢加入粉料,充分搅拌3-5分钟直至生成无粉团的、均匀的胶浆,并在操作时间内用完。建议使用机械搅拌(400-500转/分钟),以取得最佳的搅拌效果;
1. Pour the liquid additive into a clean mixing container, then mix the powder slowly while mixing proportionally, stirring fully for 3-5 minutes until the powder-free, uniform mortar is produced and used up in operation time. It is suggested that mechanical stirring (400-500 rpm) be used to obtain the best stirring effect.
2、用辊子、刷子将浆料均匀涂刷于处理好的底材上,根据使用环境及性能要求涂刷2层或2层以上; 一般工程防水层厚度为1mm,地下工程施工规范厚度要求为1.5-2mm;
2. The slurry is evenly coated on the treated substrates with rollers and brushes, and two or more layers are coated according to the use environment and performance requirements. The thickness of waterproof layer is 1 mm in general engineering and 1.5-2 mm in underground engineering construction specifications.
3、做完一层后,必须待其略为干固(刚好不粘手)后,再做第二层,一般需1-3小时,具体情况视基面的密实度以及当时的气温而定。如果超过24小时,或涂层已经固化,在其上涂刷第二层时,必须先用清水重新润湿表面;
3. After finishing the first layer, it must be slightly dry (just sticky) and then the second layer, which usually takes 1-3 hours, depending on the compactness of the base surface and the temperature at that time. If the coating has been solidified for more than 24 hours, the second layer must be wetted with clean water first.
4、养护固化:浆料涂刷后第二天起,建议用细雾喷水或湿布覆盖涂层2-3天,再进行闭水试验;对于长期盛水的水池应待其空置两周后才盛水;
4. Maintenance and solidification: From the second day after the slurry is brushed, it is suggested to cover the coating with fine mist spray or wet cloth for 2-3 days before water closure test; for long-term water-holding pond, water should be filled after two weeks of vacancy;
5、搅拌好的浆料一般宜在1小时内用完,出现凝固的材料不可再用;
5. The stirred slurry should be used up in one hour, and the solidified material can not be used again.
6、切勿掺水搅拌,也不要随意改变乳液的比例。
6, do not mix with water, and do not change the proportion of emulsion at will.